AECbytes Feature (June 02, 2004)
The Eureka
Tower: A Case Study of
Advanced BIM Implementation
The soaring
image of the Eureka Tower project, shown in Figure 1, is probably
a familiar sight to most AEC professionals who have been following
presentations and articles on building information modeling (BIM)
this past year. I made a brief reference to it myself in my June
2003 Cadence cover story, Should
We BIM? Pushing the State of the Art in AEC. Standing 92 stories
tall with a total height of 300 meters (984 feet), the Eureka Tower located in Melbourne, Australia, is not only the tallest residential
building in the world, it is also one of the largest projects to
be designed using the principles, methodology, and processes of
building information modeling.
Figure 1. A rendering of the Eureka Tower project. (Courtesy: FKA)
How exactly
was it done, and what was the technology that was used? What were
the unique challenges involved in designing this project? What was
the motivation for using BIM and how well did it work? Was the BIM methodology used by the extended design team? Is the BIM model being
used for construction and does it figure in the plans for the operation
and maintenance of the project? These are intriguing questions and
can serve as a valuable guide for the adoption and implementation
of BIM by other AEC firms across the world for their own projects.
I had the opportunity to find the answers to many of these questions
recently when I attended a presentation in San Francisco by David
Sutherland, Director of Planning at Fender Katsalidis Architects
(FKA), the Australian firm that designed the Eureka Tower project.
My findings are presented in this AECbytes feature article.
Let's start
with a brief overview of the project as well as the firm that designed
it.
Project and
Firm Overview
The Eureka Tower is located within the Southgate precinct of Melbourne, adjacent
to the Yarra River, in a landmark neighborhood comprising the Southbank
Promenade, the Arts precinct, and the Crown Casino and Entertainment
Center (see Figure 2). In addition to the residential tower that
houses the apartment units, the building includes a ten-storey podium
complex containing a parking lot and retail and office facilities,
a 3 star hotel, and an observation complex at the top featuring
public areas. The apartment sizes range from less than 100 m2 (1076
ft2) to full floor penthouses of up to 640 m2 (6890 ft2). Figure
3 shows two plans and a section through the building.
Figure 2. A night-time rendering of the Eureka Tower, showing the building
within its context. (Courtesy: FKA)
The project
was commissioned by Adam and Daniel Grollo, Tab Fried, and Nonda
Katsalidis, in a joint ventureGrocon Riverside Developments
and Michelmershformed specifically for the Eureka Tower project.
Construction on the project commenced in mid 2002, and it was scheduled
for completion in 2005. Out of a total of 92 floors for the tower,
to date the core has been constructed to level 64, and floor slabs
to level 46. Final completion is still expected in the fourth quarter
of 2005. The total budget for the residential tower is approximately
AUD 400 million (USD 280 million). The overall project budget for
the tower and the podium retail, car-parking, office, and hotel
is approximately AUD 500 million (USD 354 million).
Figure 3. Plans and section showing the design of the Eureka Tower.
(Courtesy: FKA)
It comes as
somewhat of a surprise to find that FKA, the architectural firm
that won the commission for the project, is quite young and relatively
smallit was founded in 1997 and has only 30 people. The principals
of the firm, however, are very experienced and had been involved
in other practices with each other over the past twenty-five years
before forming FKA. Since its inception, the firm has established
a reputation for itself with its award-winning high-rise residential,
commercial, and public designs in several Australian cities and
more recently also in Hong Kong, Malaysia, and Shanghai in China.
It is known for designing cutting edge buildings with sound functional
planning. In addition to the Eureka Tower, some of FKA's other well-known
projects in Australia and Asia include the Ian Potter Museum of
Art, the Republic Tower, Bendigo Art Gallery, and HM@S Beach Apartments.
Why Use BIM?
While the term
"building information modeling" had not yet been coined
at the time the design of the Eureka Tower got underway in 1998,
FKA had committed to the use of ArchiCAD which offered the 3D object-oriented,
database-driven approach to building design they were looking to
implement. The firm had long been frustrated with the limitations
of 2D CAD software, at its mimicking of manual drafting, tedium,
lack of accuracy, and its generic nature that did not allow it to
address the specific needs of architects. Being exposed to the benefits
of powerful database tools only increased this frustration and motivated
technology leaders within the firm like Sutherland to push the transition
to the 3D model-based approach.
The Eureka Tower project was seen as the ideal project to make this transition. FKA
wanted the design process to resonate with the modern and elegant
nature of the project, and be forward-looking rather than traditional.
The size of the project also played a critical role in this decision.
Recognizing that design errors account for a major portion of the
costs associated with construction errors as well as maintenance
costs, which would only be magnified in such a large project, FKA
wanted to minimize design errors as much as possible. The 3D building
modeling approach was seen as a critical means to achieve this goal,
and the firm decided to adopt it in a "pure" way: by designing
entirely in 3D and deriving the documentation as a by-product.
The fact that
the firm had very few licenses of 2D CAD drafting software made
the transition to 3D modeling software relatively easier, with little
inertia on the part of the firm's employees. The principals of the
firms were also convinced about the benefits of the model-based
approach in meeting the needs of streamlined construction programs
within an environment of strict financial and planning controls.
With regard
to the decision on which software to implement, the choice of ArchiCAD
was made based on Sutherland's exploration of model-based solutions
in the early 1990s before the formation of FKA. At that time, both
Autodesk Architectural Desktop and Autodesk Revit were still into
the future, and the only other available solution, MicroStation
Triforma, did not match up to ArchiCAD's ease of use. This was seen
as a very important criterion that would help avoid the segregation
between the "designers" and the "technology experts"
and allow everyone in the practice to be able to use the new technology
that was going to underlie the architectural process. ArchiCAD was
found simple to use yet powerful in what it could achieve. Architects,
as opposed to CAD people, could effectively use it with a minimum
of training, cutting right across the "cult of the expert."
The decision was also somewhat of a personal one for Sutherland,
who found from his interaction with the local ArchiCAD dealers and
distributors, as well as with representatives from Graphisoft, that
they were predominantly from the architectural profession and maintained
their interest in building design. He felt far more comfortable
discussing with such people issues he had with their software than
with those who were less steeped in architectural culture.
The Design
Process and Technology Workflow
Once the decision
was made to implement the model-based approach of ArchiCAD, it was
deployed right from the beginning of the project, starting with
the conceptual design. Massing models were developed of the building
and the surrounding context, and assessed in conjunction with physical
models of the building form and façade detail. Multiple design
options for the building were explored. Sun shading studies were
performed to generate shadows and analyze their impact on the surrounding
buildings. At the plan level, ArchiCAD was also used to study areas,
circulation, egress, site subdivisions, and so on.
Once the basic
building form was finalized, the conceptual 3D model was enriched
by designing and adding the details (see Figure 4). At this stage,
developing the model was almost like prototyping the building. The
model was built storey by storey, using components developed within
the application. The model then became the means to also capture
the rationale for the design, to explain why it was what it was.
This in turn allowed more dialogue and a much higher degree of interactivity
in the design process than was possible with traditional 2D CAD.
Figure 4. Adding details (right image) to the massing model shown on
the left. (Courtesy: FKA)
Because the
design was captured and explained to the clients using the 3D building
model, FKA found that highly photorealistic rendered imageswhich
are by now commonplace in architectural practicewere not usually
necessary. The design team did use Artolantis, a dedicated rendering
program that integrates well with ArchiCAD, but it was used in tandem
with the design software for exploring design issues, and not just
for rendering. Thus, rendered images of the Eureka Tower like the
ones shown here are relatively few.
Most of the
construction documentation for the project, an estimated 1000 A1
sized construction drawings, was derived directly from the 3D building
model. An example is shown in Figure 5. The drawings were further
annotated, dimensioned, detailed, and then printed using ArchiCAD's
associated plotting utility, PlotMaker. Aspects such as line weight,
dashed lines, hatching, and so on are automatically taken care of
in the derived 2D drawing, so that relatively little grunt work
is needed to finish it. Because each drawing maintains its association
with the 3D model, any change in the model automatically updates
the drawing, including the dimensions. In a project of this size,
these savings in time and the minimization of documentation errors
are magnified many times over.
Figure 5. This ArchiCAD screenshot shows a portion of the podium design
of the Eureka Tower. The construction documentation shown was derived
automatically from the 3D model (right window); only the text, dimensions,
levels, and insulation graphic were added separately. (Courtesy:
FKA)
In addition
to deriving the construction documentation, the 3D building model
was used for several other design and analysis aspects. It was used
to study the construction sequencing of the project, again very
critical in a project of this magnitude. It was useful for the interior
design, allowing material combinations and furniture layouts to
be explored. Once the interior layouts were finalized, the model
allowed the fixtures to be automatically checked against the penetration
documents. The model could not be used for cross-disciplinary collaboration,
however, since most of the consultants and other members of the
project team were still using the 2D CAD methodology. Therefore,
only the 2D drawings were shared with the extended building team,
not the 3D model. With regard to the use of the model for future
facilities management, operation, and maintenance of the building,
no firm plans have been made yet, although the availability of the
information-rich model should certainly make this a compelling option
after the construction has been completed.
Special Challenges
Imposed by the Building Size
Most architectural
practices seeking to transition from CAD to BIM would probably start
by testing it out with small pilot projects. In contrast, FKA plunged
right into the deep end of the ocean by using its largest project
to date to make the transition. It not only had to develop a new
design methodology and train the 15 to 25 member project team in
the use of the applications following this methodology, it also
had to deal with the special challenges involved in the design of
such a huge project using the BIM approach.
Having the entire
building model in one file would have been too unwieldy. To ensure
that the file sizes were within reasonable limits, the full model
was divided into several different sub-models. This subdivision
was facilitated by a hot-linking capability in ArchiCAD that was
luckily introduced just when FKA had commenced on the detailed design
development of Eureka Tower. (The version of ArchiCAD that was used
was 6.5; the current version is 8.1.) This new capability allowed
subordinate elements to be created in one file and hot-linked into
another file. That file, itself, could further be linked into another
file, with the choice of including or not including the nested information.
So, for example, a wet area fixture could be designed separately
in one file, then hot-linked into a typical apartment file, several
of which could, in turn, be hot-linked into the tower sub-model
(see Figure 6). Similarly, hot-linking was used to build up the
other sub-models, including the podium, façade, primary structure,
and so on. All these sub-models were then hot-linked to form the
full Eureka Tower model, which was 330 MB in file size and took
a full 20 minutes to load. Needless to say, the full building model
was used sparingly, and most of the design work was done using the
sub-models.
Figure 6. Bathroom fixtures such as these were created in separate
files and then hot-linked wherever needed. (Courtesy: FKA)
This entire
hierarchy of models and sub-models added up to a very complex arrangement
of information that had to be very carefully structured and managed.
However, the effort was well worth the benefit. Not only did this
allow parts of the building to be isolated into smaller and simpler
models that could be used to study and design variations, it also
allowed components and assemblies to be designed once and re-used
across the project. Any change made in a sub-model would be automatically
reflected in all the parent-level models that the sub-model was
hot-linked into. One member of the design team acted as a dedicated
"Model Manager" who was responsible for checking the correctness
of the full 3D model at all times.
With regard
to workstation resources, FKA was able to implement the Eureka Tower project on standard computers that architects can afford. It did,
however, need to upgrade its network, hubs, and graphics cards to
be able to work more efficiently. The firm's resources were utilized
to their fullest capacity, and conversely, the BIM approach was
implemented to the fullest extent of the available computing power
and time.
Other Benefits
of the BIM Approach
In the course
of implementing the BIM approach for the Eureka Tower project, FKA
has found that its benefits extend far beyond just the project in
which it is used to the firm as a whole. The advanced use of technology
has flattened the traditional hierarchical management structure
and reduced the divide between the older design principals and the
younger technologically-savvy staff. BIM allows for a process in
which there is no division between design and documentation, and
therefore eliminates the need for dedicated draftspeople who only
do documentation. Since the documentation is now achieved as a byproduct,
everyone involved in a project concentrates on the design, and is
required to collaborate effectively with the other team members.
Thus, BIM enhances cooperation rather than segregation between the
employees of the firm.
With regard
to the project itself, the ability to visualize the building in
3D leads to a much better understanding of the design. Multiple
design options can be easily explored, and subjected to a higher
degree of analysis and evaluation than would have been possible
with traditional 2D CAD. The increased focus on analysis allows
better decision-making and leads to a functionally sound building.
The practice of architecture itself becomes like a performing art
and is a lot more enjoyable.
In the case
of the Eureka Tower project, the use of BIM did not extend to other
disciplines since the consultants were not yet ready to give up
their standard 2D CAD based processes. The benefits would have been
even more remarkable had it done so.
Conclusions
One of the most
frequent questions asked by AEC professionals when building information
modeling is discussed is: "Who will pay for the extra effort
to develop the model?" (See my write-up on the AIA-TAP 2003
conference in Cadence
AEC Tech News #108.) FKA has not let issues such as these hold
them back from what they see as the most logical means to design
a building using the capabilities of the technology that is currently
available. It now sees BIM as the standard way of doing business
within the firm and does not expect to receive a higher compensation
than its regular fee for its implementation of BIM. The internal
benefits have been found to be well worth the extra cost and effort,
even for the first project. Subsequent projects should be able to
reap the same benefits with much less cost and effort.
Acknowledgements
I would like
to thank David Sutherland of FKA for taking the time to communicate
with me at depth about the Eureka Tower project, and for supplying
all the images used in this article.
About the Author
Lachmi Khemlani is founder and editor of AECbytes. She has a Ph.D. in Architecture from UC Berkeley, specializing in intelligent building modeling, and
consults and writes on AEC technology. She can be reached at lachmi@aecbytes.com.
If you found this article useful and have not yet subscribed to AECbytes, please consider doing so. Subscription is free, and more subscribers will allow this publication to provide more of such content to you.
Features >The Eureka Tower> Printer-friendly format
|